Midwestern Services performed the clean-out and roof removal of T611 in preparation for the tanks demolition. I stopped by the location yesterday, unannounced. The crew was wrapping up for the day. To be sure, they had moved over 400bbl of liquid into a frac tank and began demo of the roof. There was not any oil, residue, refuse anywhere on the ground.

This is by far, the most organized, well laid out equipment for a confined space entry operation I’ve ever seen. I’ve spoken with Midwestern and made sure they know how pleased, from and HSSE standpoint, we are of the project so far.

Russ Miller
Genesis Energy, L.P.
HSSE Manager